Pulling together background data to identify local trip patterns.
Community Engagement
November 2023
-
February 2024
Gathering views from the community to help shape the routes/improvements and inform the final network.
Define Final Network Maps
February 2024
-
March 2024
Following on from feedback provided by the local community engagement, we will define our final network maps.
Audit and Prioritise routes
March 2024
-
April 2024
Once the final network has been defined, the chosen routes will be audited and prioritised based on the outcomes.
Final Reporting
April 2024
-
May 2024
Once routes have been prioritised, we will identify the recommended improvements and produce a final LCWIP report for each area.
You will have another chance to comment at this stage.