Calne and Melksham LCWIP

Milestones

  • Develop an Evidence Base and Draft Network

    June 2023

     

    -

     

    November 2023

    Pulling together background data to identify local trip patterns.
  • Community Engagement

    November 2023

     

    -

     

    February 2024

    Gathering views from the community to help shape the routes/improvements and inform the final network.
  • Define Final Network Maps

    February 2024

     

    -

     

    March 2024

    Following on from feedback provided by the local community engagement, we will define our final network maps.
  • Audit and Prioritise routes

    March 2024

     

    -

     

    April 2024

    Once the final network has been defined, the chosen routes will be audited and prioritised based on the outcomes.
  • Final Reporting

    April 2024

     

    -

     

    May 2024

    Once routes have been prioritised, we will identify the recommended improvements and produce a final LCWIP report for each area. You will have another chance to comment at this stage.